Four projects people mix up
Prices for a "garage conversion" can disagree by a factor of ten because they often describe different projects.
Garage turned into a room
- What it is:
- A bedroom, office, gym or den that stays part of the main house. Not a separate unit.
- Size:
- No state ADU size rules apply.
- Parking:
- Your city's own parking rules apply. The state no-replacement rule is written for ADUs.
- Approval:
- A regular building permit from your city.
Garage converted to an ADU
- What it is:
- A separate home with complete independent living facilities, in an attached or detached garage.
- Size:
- Uses the existing shell. A detached garage may grow up to 150 square feet, only to fit an entry or exit such as a stairway.
- Parking:
- No replacement parking for the lost garage spaces, and no parking for the ADU itself.
- Approval:
- State approval clock (see below).
Junior ADU
- What it is:
- A unit inside the house, which can include an attached garage. Can share a bathroom with the house.
- Size:
- No more than 500 square feet of interior livable space. Own entrance and at least an efficiency kitchen.
- Parking:
- No parking can be required, even when it is converted from an attached garage.
- Approval:
- State approval clock. A city can require the owner to live on site only if it shares a bathroom with the house.
New detached ADU
- What it is:
- A new building on the lot, with its own foundation, roof and utility runs.
- Size:
- A city must allow at least 800 square feet with 4 foot side and rear setbacks.
- Parking:
- At most one space per unit or bedroom, and none within half a mile walk of public transit.
- Approval:
- State approval clock, plus a demolition permit issued at the same time if it replaces a detached garage.
Do you have to replace the parking?
Not for an ADU. Under Government Code section 66314, when a garage, carport or parking space is converted to an ADU, or torn down to build one, the city cannot require those spaces to be replaced. Section 66322 adds that a city cannot impose any parking standard on an ADU that is part of the house or of an existing accessory structure, or on one within half a mile walking distance of public transit. For a room conversion, ask the planning counter about parking before you design.

Permits and the approval clock
Plan on a building permit for any of these. For an ADU or junior ADU, Government Code section 66317 also sets the process:
- Approval is ministerial, which means no discretionary review and no public hearing.
- The city has 15 business days to tell you in writing whether the application is complete, with a list of anything missing.
- It then has 60 days to approve or deny a complete application when there is already a house on the lot. If it misses that, the application is deemed approved.
- A denial has to come with written comments on what is wrong and how to fix it, and you can appeal in writing.
More on permits in building permits in Orange County, and on contracts in how much a contractor can ask for up front.
Setbacks, size and fire safety
- No new setbacks for a conversion. A city cannot require a setback for an existing structure converted to an ADU, or for one rebuilt in the same place and to the same size.
- Exterior access and fire safety. A converted ADU or junior ADU needs its own exterior access, and side and rear setbacks sufficient for fire and safety. HCD notes that a conversion has to meet the building, health and fire standards for a home, not a garage.
- Fire sprinklers. Not required if the main house does not require them, and adding an ADU cannot trigger sprinklers in the main house.
- Size caps. A city cannot cap an ADU below 850 square feet, or 1,000 square feet with more than one bedroom.
Can you do more than one?
Yes. Government Code section 66323 lets you combine one converted ADU and one junior ADU inside the house or an existing accessory structure with one new detached ADU of up to 800 square feet on a single-family lot. So a garage conversion does not rule out a backyard unit later. Only one junior ADU is allowed per lot.

How the cost compares
A conversion usually costs less than a new detached ADU because the walls, roof and foundation are already there. The money goes to insulation, drywall, windows and doors, plumbing and a sewer connection for a kitchen and bathroom, electrical work, and finishes. We found no published survey figure for garage conversions, so we do not print one.
For the detached end, according to the Remodeling 2025 Cost vs. Value Report (www.costvsvalue.com), a new 660 square foot, one-story detached ADU averaged $178,536 in the Los Angeles market in 2025, the closest market it covers to Orange County. Our ADU cost guide covers what drives it, and the 2026 law changes, including the SB 543 limits on impact fees for smaller units.
Pre-approved plans in Orange County
Newport Beach is the one Orange County city we found whose pre-approved plans include garage conversions: two of its five, one for a one-car garage and one for a two-car garage. You still supply site-specific items such as a site plan and a Title 24 energy analysis (the state energy code form). Other cities' plan programs are in the city table of our ADU cost guide.
HOAs and the coastal zone
An HOA (homeowners association) can apply reasonable design rules to an ADU but cannot effectively prohibit one (Civil Code section 4751); a room conversion gets no such protection. In the coastal zone, an ADU can also need a coastal development permit. Both are covered in our guide to HOA and coastal approvals.
Frequently asked questions
What is the difference between a garage conversion and an ADU?
A garage becomes an ADU only when it is turned into a separate home with complete independent living facilities. A bedroom, gym or office is not a unit, so the state ADU rules do not cover it.
Can I convert my garage into a junior ADU?
An attached garage, yes, because state law counts it as part of the house. A detached garage can become a regular ADU but not a junior ADU.
The ADU cost figure is from the Remodeling 2025 Cost vs. Value Report (www.costvsvalue.com) for the Los Angeles market. © 2025 Zonda Media, a Delaware Corporation. Complete data from the Remodeling 2025 Cost vs. Value Report can be downloaded free at www.costvsvalue.com. OakTend is not a contractor and does not set or guarantee prices.
Sources
- California Government Code section 66313
An ADU provides complete independent living facilities on a lot with a primary residence; a junior ADU is no more than 500 square feet of interior livable space and contained entirely within a single-family residence. - California Government Code section 66314
An ADU may be within or attached to the home, including an attached garage, or detached, including a detached garage (d)(3); no setback for an existing structure converted to an ADU, and no more than 4 feet side and rear for a new one (d)(7); no replacement of parking when a garage, carport or parking space is converted to or demolished for an ADU (d)(11); no fire sprinklers if the primary residence is not required to have them (d)(12). - California Government Code section 66317 (as amended by SB 543, effective January 1, 2026)
ADU approval is ministerial with no hearing; the permitting agency has 15 business days to give written notice whether an application is complete; it must approve or deny within 60 days of a complete application when a dwelling exists, or the application is deemed approved; a denial comes with written comments; there is a written appeal process. - California Government Code section 66321
A city cannot cap ADU size below 850 square feet, or 1,000 square feet with more than one bedroom. - California Government Code section 66322
No parking standards for an ADU within one-half mile walking distance of public transit, or one that is part of the proposed or existing primary residence or an accessory structure, among other cases. - California Government Code section 66323
A city must ministerially approve any combination of one ADU and one junior ADU within the existing space of a single-family dwelling or accessory structure (up to 150 square feet of expansion of an accessory structure, limited to ingress and egress; exterior access; setbacks sufficient for fire and safety) and one detached new ADU with 4-foot side and rear setbacks, which a city may limit to no less than 800 square feet. - California Government Code section 66333 (as amended by AB 1154, effective January 1, 2026)
A junior ADU needs a separate entrance and an efficiency kitchen; enclosed uses within the residence, such as attached garages, are part of the residence; owner-occupancy may be required only when the junior ADU shares sanitation facilities; a junior ADU rental must be for more than 30 days. - California Department of Housing and Community Development: Accessory Dwelling Unit Handbook (March 2026)
No parking may be required for a junior ADU, even when converted from an attached garage; junior ADUs are not allowed in detached accessory structures and only one is allowed per lot; ADU conversions are subject to all applicable building, health and safety, and fire standards for dwellings; the 150 square foot expansion example is a stairwell; ADU parking may not exceed one space per unit or bedroom; a demolition permit for a detached garage replaced by an ADU is issued at the same time as the ADU permit. - California Senate Bill 543 (2025-2026), chaptered text (Chapter 520, approved October 10, 2025)
No impact fee on an ADU with 750 square feet or less of interior livable space or a junior ADU of 500 square feet or less; above 750 square feet, impact fees are proportional to the primary dwelling; units under 500 square feet of interior livable space are treated as not triggering school fees. - City of Newport Beach: ADU standard plans
Newport Beach offers five pre-reviewed standard ADU plans: three detached units and two garage conversions (Plan 4, one-car garage; Plan 5, two-car garage); supplemental items such as a site plan and Title 24 energy analysis are still required. - Remodeling 2025 Cost vs. Value Report (www.costvsvalue.com): Los Angeles, California
A new 660 square foot, one-story detached ADU averaged $178,536 in the Los Angeles market in 2025. The report has no separate Orange County market. - California Civil Code section 4751
HOA rules that effectively prohibit or unreasonably restrict an ADU or junior ADU on a single-family lot are void and unenforceable; reasonable restrictions are allowed.